Waterend Update

Waterend

Update 30th May

Facia boards on and front end of cabin looking good

IMG-20160530-WA0000

Update for 18th May 2016

Roof completed on the main cabin and concrete laid to extend the hard standing area. Old container removed as was no longer water tight. Toilet block has been ordered.

Layout of new toilet block

IMG_0422

Photos of building work carried out

New Roof

IMG_0430

Hard Standing

IMG_0431IMG_0434IMG_0433IMG_0432

We plan to complete for the start of the 2016/17 season.

Update for 7th May 2016

Internal walls started to be constructed for the changing rooms. Admin cabin cleaned out for Tournament

IMG_0419 IMG_0418 IMG_0417 IMG_0416 IMG_0415 IMG_0414 IMG_0414 - Copy IMG_0413 - Copy IMG_0413 IMG_0412 IMG_0412 - Copy

Updated 4th May 2016

happy face Building work has actually started.happy face

Over the weekend of the 30th April and 1st May building work started on the refurbishment of the cabins at Waterend. For those who have visited this week you will see. Here are some photos of the team in action.

We plan to finish the roof the weekend of the 7th May with the concrete being laid the weekend of the 14th so if you wish to assist please let us know.

13124687_1288679107828874_5707657826043261073_n 13133230_1288679044495547_5074064262363795202_n 13139027_1288678971162221_336310323298823050_n 13119093_1288679061162212_4603886124804313648_n 13062289_1288679161162202_7129775170526755598_n 13062435_1288678951162223_6559503166840973660_n 13077094_1288679001162218_4042964592208130572_n 13077088_1288679091162209_5473895440911640288_n 13092054_1288679024495549_968870859334121976_n

 